Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Power Mech Projects Ltd | 20078957 | GOPALPUR TELHAI, GANGA RAMPUR | 296.00 | 68.59 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 10 | NA | No | 13629.00 | 13500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Hathgaon | Ganga Rampur | 428245 | Ganga Rampur | 141 | 111 | 79 | Work In Progress | Not Certified |
| 2 | Fatehpur | Hathgaon | Ganga Rampur | 428246 | Chak Hasanpur | 53 | 7 | 13 | Work In Progress | Not Certified |
| 3 | Fatehpur | Hathgaon | Ganga Rampur | 428247 | Abdullapur | 101 | 35 | 35 | Work In Progress | Not Certified |
| 4 | Fatehpur | Hathgaon | Gopalpur Telhai | 428251 | Gopalpur Telahi | 169 | 145 | 86 | Work In Progress | Not Certified |
| 5 | Fatehpur | Hathgaon | Gopalpur Telhai | 428252 | Chak Shah Kabir | 63 | 61 | 97 | Work In Progress | Not Certified |