Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20078959 | BARWA SUKHDEV GOGP | 444.48 | 234.38 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 15667.00 | 13485.30 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Tamkuhi Raj | Barwa Sukhdev | 458674 | Barwa Sukhdav | 241 | 241 | 100 | Har Gar Jal | Not Certified |
| 2 | Kushi Nagar | Tamkuhi Raj | Belwa Bujurg | 458675 | Belwa Buzurg | 292 | 272 | 93 | Work In Progress | Not Certified |
| 3 | Kushi Nagar | Tamkuhi Raj | Jhankaul | 458816 | Jhankaul | 302 | 302 | 100 | Har Gar Jal | Not Certified |