Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Power Mech Projects Ltd | 20078966 | ISHAKPUR,IMADPUR | 375.00 | 83.44 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 10 | NA | No | 28042.00 | 24906.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Hathgaon | Imadpur | 428206 | Imadpur | 181 | 181 | 100 | Har Gar Jal | Not Certified |
| 2 | Fatehpur | Hathgaon | Imadpur | 428207 | Rajjipur | 118 | 33 | 28 | Work In Progress | Not Certified |
| 3 | Fatehpur | Hathgaon | Ishakpur | 428216 | Ishakpur | 179 | 179 | 100 | Har Gar Jal | Not Certified |
| 4 | Fatehpur | Hathgaon | Ishakpur | 428217 | Kharhara | 91 | 20 | 22 | Work In Progress | Not Certified |
| 5 | Fatehpur | Hathgaon | Ishakpur | 428218 | Rahimanpur | 53 | 46 | 87 | Work In Progress | Not Certified |
| 6 | Fatehpur | Hathgaon | Imadpur | 681276 | Ghanshyampur | 36 | 2 | 6 | Work In Progress | Not Certified |
| 7 | Fatehpur | Hathgaon | Ishakpur | 681277 | Saidanpur Kanti | 42 | 2 | 5 | Work In Progress | Not Certified |