Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Fatehpur
AGENCY Power Mech Projects Ltd
SCHEME ID 20078999
SCHEME NAME CHAK ITAULI&SARULI
ESTIMATED COST 293.00
EXPENDITURE 98.13
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 21
Procured 21 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 17770.00 Meter
Length Laid 15425.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Fatehpur Hathgaon Chak Itaili 428215 Chak Itaili 338 326 96% Work In Progress Not Certified
2 Fatehpur Hathgaon Sarauli 428338 Sarauli 180 12 7% Work In Progress Not Certified
3 Fatehpur Hathgaon Sarauli 428339 Gokulpur 69 51 74% Work In Progress Not Certified
4 Fatehpur Hathgaon Sarauli 428340 Chak Sarauli 30 23 77% Work In Progress Not Certified