Scheme Details
DISTRICT
Fatehpur
AGENCY
Power Mech Projects Ltd
SCHEME ID
20079037
SCHEME NAME
MAMREJPUR&REWARI KHURD
ESTIMATED COST
321.17
EXPENDITURE
111.35
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14605.00
Meter
Length Laid
15000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Malwan | Mamrejpur | 427467 | Mamrejpur | 235 | 215 | 91% | Work In Progress | Not Certified |
| 2 | Fatehpur | Malwan | Rewari Khurd | 427484 | Rewari Khurd | 244 | 160 | 66% | Work In Progress | Not Certified |