Scheme Details
DISTRICT
Sambhal
AGENCY
SPML Infra
SCHEME ID
20079312
SCHEME NAME
Alawalpuri GP W/S Scheme
ESTIMATED COST
262.97
EXPENDITURE
119.66
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7778.00
Meter
Length Laid
5366.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Baniakhera | Alawalpuri | 388703 | Alawalpuri | 253 | 244 | 96% | Work In Progress | Not Certified |
| 2 | Sambhal | Baniakhera | Alawalpuri | 388704 | Bhataur | 228 | 211 | 93% | Work In Progress | Not Certified |