DISTRICT Etah
AGENCY JMC - Lakshmi (JV)
SCHEME ID 20079417
SCHEME NAME REJUA AND SALAMAI GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 279.35
EXPENDITURE 151.95
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 50
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15888.00 Meter
Length Laid 11623.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etah Awagarh Rejua 399922 Rejua 497 482 97% Work In Progress Not Certified
2 Etah Awagarh Silamai 399923 Salamai 172 150 87% Work In Progress Not Certified