Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20079467 | Damkhoda & Basant nagar jagir Water Supply Scheme | 445.72 | 225.11 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 35 | 35 | Yes | 0 | NA | No | 15044.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Damkhoda | Damkhoda | 402914 | Damkhoda | 618 | 613 | 99 | Work In Progress | Not Certified |
| 2 | Bareilly | Damkhoda | Damkhoda | 402915 | Damkhudia | 96 | 92 | 96 | Work In Progress | Not Certified |
| 3 | Bareilly | Damkhoda | Basant Nagar Jagir | 402916 | Basant Nagar Jagir | 284 | 252 | 89 | Work In Progress | Not Certified |