Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20079488
SCHEME NAME
Nabi Nagar Water Supply Scheme
ESTIMATED COST
314.56
EXPENDITURE
164.05
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9237.00
Meter
Length Laid
9237.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Kyara | Nabi Nagar | 403305 | Nabi Nagar | 734 | 734 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bareilly | Kyara | Nabi Nagar | 403306 | Jhingri | 66 | 10 | 15% | Work In Progress | Not Certified |