Scheme Details
DISTRICT Baghpat
AGENCY LC INFRA
SCHEME ID 20080078
SCHEME NAME BHAGOT W/S SCHEME
ESTIMATED COST 260.91
EXPENDITURE 186.98
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 35
Procured 35 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7213.00 Meter
Length Laid 7000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Baghpat Khekara Bhagot 392182 Bhagot 615 603 98% Work In Progress Not Certified