Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20080876
SCHEME NAME
SIKADIKOL VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
357.50
EXPENDITURE
142.94
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13798.00
Meter
Length Laid
11950.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Dohri Ghat | Sikadikol | 464941 | Sikari Kol | 558 | 550 | 99% | Work In Progress | Not Certified |
| 2 | Mau | Dohri Ghat | Sikadikol | 464943 | Tal Patachh | 23 | 23 | 100% | Har Ghar Jal | Not Certified |
| 3 | Mau | Dohri Ghat | Sikadikol | 464944 | Jamin Sarang Pur | 136 | 130 | 96% | Work In Progress | Not Certified |