Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20080926 | Bhanpur Malhapur & Khana Mador Water Supply Scheme | 393.81 | 170.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 12924.00 | 12924.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Behta | Bhanpur Mallapur | 410745 | Bhanpur Malhapur | 243 | 241 | 99 | Work In Progress | Not Certified |
| 2 | Sitapur | Behta | Bhanpur Mallapur | 410746 | Lakhaneepur | 155 | 154 | 99 | Work In Progress | Not Certified |
| 3 | Sitapur | Behta | Khana Maror | 410817 | Khana Maror | 194 | 188 | 97 | Work In Progress | Not Certified |