Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20081285 | NAGSAR REORGANISATION W/S SCHEME (VSA) | 1055.90 | 413.92 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Revatipur | Gagran | 473964 | Gagran | 455 | 353 | 78 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Revatipur | Nagsar Newajurai | 473974 | Nagsar Newajurai | 786 | 723 | 92 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Revatipur | Nagsar Newajurai | 473975 | Piajua | 105 | 81 | 77 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Revatipur | Nagsar Newajurai | 473976 | Dohala | 23 | 22 | 96 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Revatipur | Nagsar Mir Rai | 473977 | Nagsar Mir Rai | 217 | 132 | 61 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 84 | 84 | Yes | 0 | NA | No | 32577.00 | 30647.00 |