Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20081474 | KAJARI JAMALUDDINPUR WSS | 353.80 | 236.94 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 12052.00 | 12052.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Akbarpur | Sulhantara | 439058 | Ismailpur Dubkhar | 92 | 89 | 97 | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Akbarpur | Sulhantara | 439059 | Sulhantara | 154 | 154 | 100 | Har Gar Jal | Not Certified |
| 3 | Ambedkar Nagar | Akbarpur | Kajari Jamaluddinpur | 439102 | Kajri Jamaluddinpur | 268 | 262 | 98 | Work In Progress | Not Certified |