Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sitapur
AGENCY Larsen & Toubro Ltd
SCHEME ID 20081593
SCHEME NAME Kuchkapur Water Supply Scheme
ESTIMATED COST 267.96
EXPENDITURE 73.75
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7493.00 Meter
Length Laid 7010.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Ealliya Kuchkapur 410231 Kuchkapur 428 421 98% Work In Progress Not Certified