Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20081713 | RAIPUR KHAS | 324.63 | 227.36 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 10434.00 | 10622.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Nebua Naurangiya | Raipur Bhaisahi | 457595 | Raipur Bhaisahi | 322 | 322 | 100 | Har Gar Jal | Certified |
| 2 | Kushi Nagar | Nebua Naurangiya | Rampur Khas | 457597 | Rampur Khas | 286 | 286 | 100 | Har Gar Jal | Certified |