Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20081813 | SUDHIYANI | 459.14 | 273.24 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 14030.00 | 13494.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Kaptanganj | Belbhadra Chhapra | 458085 | Belbhadra Chhapra | 221 | 221 | 100 | Har Gar Jal | Not Certified |
| 2 | Kushi Nagar | Kaptanganj | Sudhiyani | 458101 | Sudhiyani | 649 | 649 | 100 | Har Gar Jal | Not Certified |