Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20082320 | GAURI SHRIRAM | 1133.00 | 436.55 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 1 | 2 | 2 | 2 | 2 | 2 | 0 | 0 | 88 | 88 | Yes | 0 | NA | No | 53.99 | 38392.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Dudhahi | Gauri Shri Ram | 458865 | Gauri Shri Ram | 2033 | 2033 | 100 | Har Gar Jal | Certified |