Scheme Details
DISTRICT
Amethi
AGENCY
Gayatri Projects LTD
SCHEME ID
20082417
SCHEME NAME
KARANGAON & USUF NAGAR WATER SUPPLY SCHEME
ESTIMATED COST
730.10
EXPENDITURE
663.80
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
54
Procured
54
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
26991.00
Meter
Length Laid
26991.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Amethi | Singhpur | Karan Gaon | 416400 | Karan Gaon | 623 | 623 | 100% | Har Ghar Jal | Certified |
| 2 | Amethi | Singhpur | Usufnagar | 416405 | Usufnagar | 429 | 429 | 100% | Har Ghar Jal | Certified |