Scheme Details
DISTRICT
Meerut
AGENCY
Power Mech Projects Ltd
SCHEME ID
20082569
SCHEME NAME
SHIRJEPUR HADIPUR GAORI KISHANPUR LATIFPUR KANKAR KHERA
ESTIMATED COST
497.22
EXPENDITURE
336.06
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17395.00
Meter
Length Laid
14630.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Meerut | Hastinapur | Latifpur | 391497 | Kanker Khera | 290 | 288 | 99% | Work In Progress | Not Certified |
| 2 | Meerut | Hastinapur | Latifpur | 391498 | Latifpur | 517 | 515 | 100% | Work In Progress | Not Certified |
| 3 | Meerut | Hastinapur | Shirjepur | 391540 | Kishanpur | 35 | 32 | 91% | Work In Progress | Not Certified |
| 4 | Meerut | Hastinapur | Shirjepur | 391543 | Shirjepur | 131 | 125 | 95% | Work In Progress | Not Certified |
| 5 | Meerut | Hastinapur | Shirjepur | 391545 | Hadipur Gaori | 26 | 21 | 81% | Work In Progress | Not Certified |