Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20083032 | NAWALI REORGANISATION W/S SCHEME (VSA) | 2184.00 | 820.91 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Revatipur | Utrauli | 473958 | Utrauli | 1160 | 882 | 76 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Revatipur | Nawali | 473978 | Nawali | 2226 | 2021 | 91 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Revatipur | Tirlokpur | 474007 | Tirlokpur | 592 | 394 | 67 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 6 | 6 | 6 | 6 | 3 | 0 | 0 | 189 | 189 | Yes | 0 | NA | No | 76636.00 | 75521.00 |