Scheme Details
DISTRICT
Ghazipur
AGENCY
VSA
SCHEME ID
20083208
SCHEME NAME
MARDAHA REORGANISATION W/S SCHEME (VSA)
ESTIMATED COST
2134.70
EXPENDITURE
513.58
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
11
T/W Progress
Required
9
Boring Done
9
Air Compressor Done
9
O.P. Unit Done
9
OHT Progress
Required
4
Work Started
0
Work Completed
0
Solar Plant
Required
123
Procured
123
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
73037.00
Meter
Length Laid
72587.00
Meter
Scheme Assigned Villages
11 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mardah | Kardah Kaithawali | 472652 | Kardah Kaithawali | 266 | 266 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Mardah | Kansahari | 472656 | Kansahari | 119 | 119 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ghazipur | Mardah | Kansahari | 472657 | Kabeerpur | 88 | 70 | 80% | Work In Progress | Not Certified |
| 4 | Ghazipur | Mardah | Kansahari | 472658 | Bijwanpur | 70 | 68 | 97% | Work In Progress | Not Certified |
| 5 | Ghazipur | Mardah | Narwar | 472685 | Narwar | 297 | 266 | 90% | Work In Progress | Not Certified |
| 6 | Ghazipur | Mardah | Nonara | 472692 | Nonara | 214 | 203 | 95% | Work In Progress | Not Certified |
| 7 | Ghazipur | Mardah | Pandita | 472693 | Pandita | 195 | 118 | 61% | Work In Progress | Not Certified |
| 8 | Ghazipur | Mardah | Mardah | 472737 | Mardah | 1110 | 1039 | 94% | Work In Progress | Not Certified |
| 9 | Ghazipur | Mardah | Mardah | 472738 | Araji Ghurma | 66 | 51 | 77% | Work In Progress | Not Certified |
| 10 | Ghazipur | Mardah | Mahegwan | 472741 | Mahegwan | 203 | 203 | 100% | Har Ghar Jal | Not Certified |
| 11 | Ghazipur | Mardah | Mahegwan | 472742 | Deevan Patti | 100 | 90 | 90% | Work In Progress | Not Certified |