Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20083227 | TIARA REORGANISATION W/S SCHEME (VSA) | 1070.92 | 310.17 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 5 | 5 | 5 | 5 | 2 | 2 | 0 | 70 | 70 | NA | 0 | NA | No | 43675.00 | 42230.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Virno | TIYARA | 472545 | TIARA | 760 | 700 | 92 | Work In Progress | Not Certified |
| 2 | Ghazipur | Virno | Birno | 472571 | Birno | 716 | 494 | 69 | Work In Progress | Not Certified |