Scheme Details
DISTRICT
Shahjahanpur
AGENCY
NCC Ltd.
SCHEME ID
20084139
SCHEME NAME
JORA BHUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
218.49
EXPENDITURE
98.91
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
11
Procured
11
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8424.00
Meter
Length Laid
8424.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Madnapur | Jaura Bhud | 636685 | Jaura Bhud | 221 | 217 | 98% | Work In Progress | Not Certified |