Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Azamgarh
AGENCY SIEPL – BRCCPL (JV) / SKYLARK
SCHEME ID 20084151
SCHEME NAME Kota Bujurg Water Supply Scheme
ESTIMATED COST 255.24
EXPENDITURE 69.82
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12959.00 Meter
Length Laid 12955.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Azamgarh Lalganj Kaotabujurg 464240 Kaotabujurg 281 275 98% Work In Progress Not Certified
2 Azamgarh Lalganj Kaotabujurg 464241 Raypurparsyia 11 1 9% Work In Progress Not Certified
3 Azamgarh Lalganj Kaotabujurg 464242 Belgahna 44 43 98% Work In Progress Not Certified
4 Azamgarh Lalganj Kaotabujurg 464243 Govind Pur Majid 20 20 100% Har Ghar Jal Not Certified