Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20084164
SCHEME NAME
BAGHIYARI CHOUGWAN JJM
ESTIMATED COST
350.26
EXPENDITURE
273.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14456.00
Meter
Length Laid
14456.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Bilagram | BAGHIYARI CHAUNGAWAN | 412713 | BAGHIYARI CHAUNGAWAN | 215 | 215 | 100% | Har Ghar Jal | Not Certified |
| 2 | Hardoi | Bilagram | BAGHIYARI CHAUNGAWAN | 412714 | FAIZPUR KAMPOO | 77 | 77 | 100% | Har Ghar Jal | Not Certified |
| 3 | Hardoi | Bilagram | BAGHIYARI CHAUNGAWAN | 412717 | BOCHANPUR | 20 | 20 | 100% | Har Ghar Jal | Not Certified |