Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20084259 | KALYANMAL JJM | 1038.51 | 675.52 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 39 | 39 | Yes | 0 | NA | No | 46397.00 | 46397.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | KOTHAWAN | KALYANMAL | 413287 | KALYANMAL | 1699 | 1679 | 99 | Work In Progress | Not Certified |
| 2 | Hardoi | KOTHAWAN | KALYANMAL | 413288 | ATSALIYA BHOORH | 155 | 142 | 92 | Work In Progress | Not Certified |
| 3 | Hardoi | KOTHAWAN | KALYANMAL | 413289 | KEEMA | 92 | 91 | 99 | Work In Progress | Not Certified |