Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20084316
SCHEME NAME
TOLWA AANT JJM
ESTIMATED COST
916.77
EXPENDITURE
516.30
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
30833.00
Meter
Length Laid
30833.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | HARIYAWAN | TOLWA AANT | 412789 | TOLWA AANT | 440 | 440 | 100% | Har Ghar Jal | Not Certified |
| 2 | Hardoi | HARIYAWAN | TOLWA AANT | 412790 | KALWARI GRANT | 40 | 40 | 100% | Har Ghar Jal | Not Certified |