Scheme Details
DISTRICT
Shahjahanpur
AGENCY
NCC Ltd.
SCHEME ID
20084382
SCHEME NAME
VAIDAPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
204.59
EXPENDITURE
99.33
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
11
Procured
11
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6016.00
Meter
Length Laid
6016.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Nigohi | Vaidapur | 406935 | Paidapur | 122 | 120 | 98% | Work In Progress | Not Certified |
| 2 | Shahjahanpur | Nigohi | Vaidapur | 406937 | Mishripur | 74 | 70 | 95% | Work In Progress | Not Certified |
| 3 | Shahjahanpur | Nigohi | Vaidapur | 406938 | Vaidapur | 110 | 105 | 95% | Work In Progress | Not Certified |