Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20084399
SCHEME NAME
DEVRAHAR & CHANDELPUR WSS
ESTIMATED COST
240.34
EXPENDITURE
197.24
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11954.00
Meter
Length Laid
11954.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Dubepur | Devrahar | 440440 | Devrahar | 164 | 164 | 100% | Har Ghar Jal | Certified |
| 2 | Sultanpur | Dubepur | Devrahar | 440507 | Chandelepur | 164 | 164 | 100% | Har Ghar Jal | Not Certified |