Scheme Details
DISTRICT
Sant Kabeer Nagar
AGENCY
JAKSON
SCHEME ID
20084526
SCHEME NAME
GULARIHIYA GP WSS
ESTIMATED COST
160.39
EXPENDITURE
145.22
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6328.00
Meter
Length Laid
7224.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Baghauli | Gularihiya | 452260 | Atraura | 108 | 108 | 100% | Har Ghar Jal | Certified |
| 2 | Sant Kabeer Nagar | Baghauli | Gularihiya | 452261 | Gularihiya | 165 | 165 | 100% | Har Ghar Jal | Certified |