| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Megha | 20084898 | Basantpur Water Supply Scheme | 292.00 | 122.20 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 18135.00 | 13718.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Puredalai | Sikrohra | 435670 | Sikrohra | 177 | 170 | 96 | Work In Progress | Not Certified |
| 2 | Barabanki | Puredalai | Basant Pur | 435682 | Basant Pur | 211 | 206 | 98 | Work In Progress | Not Certified |
| 3 | Barabanki | Puredalai | Basant Pur | 435684 | Gadhi | 65 | 61 | 94 | Work In Progress | Not Certified |