Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20084936 | JAFARPUR WSS | 411.93 | 243.15 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 27605.00 | 25505.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jalalpur | Jafarpur | 438319 | Nasavpur | 145 | 143 | 99 | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Jalalpur | Jafarpur | 438320 | Jafarpur | 162 | 160 | 99 | Work In Progress | Not Certified |
| 3 | Ambedkar Nagar | Jalalpur | Gayaspur | 438398 | LARPUR NORTH | 39 | 39 | 100 | Har Gar Jal | Not Certified |
| 4 | Ambedkar Nagar | Jalalpur | Gaura Kamal | 438399 | Gaura Kamalpur | 192 | 188 | 98 | Work In Progress | Not Certified |