| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20085058 | KATHAUTIYA SANDDIH &PIRAILA GP wss | 304.93 | 158.58 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 20858.00 | 20000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Kathautiya Sanddih | 449348 | Kathautiya Sanddih | 202 | 185 | 92 | Work In Progress | Not Certified |
| 2 | Basti | Gaur | Piraila | 449369 | Kapurpur | 72 | 61 | 85 | Work In Progress | Not Certified |
| 3 | Basti | Gaur | Piraila | 449370 | Piraila | 83 | 68 | 82 | Work In Progress | Not Certified |
| 4 | Basti | Gaur | Piraila | 449371 | Parsa | 18 | 11 | 61 | Work In Progress | Not Certified |