Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20085073 | DEOKHER GP wss | 287.86 | 145.45 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 17689.00 | 17100.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Vikramjot | Deokher | 450047 | Araji Deokhar | 34 | 34 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Vikramjot | Deokher | 450048 | Jot Asre | 28 | 28 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Vikramjot | Deokher | 450049 | Musaha | 35 | 35 | 100 | Har Gar Jal | Not Certified |
| 4 | Basti | Vikramjot | Deokher | 450050 | Devapur | 38 | 38 | 100 | Har Gar Jal | Not Certified |
| 5 | Basti | Vikramjot | Deokher | 450051 | Gangapur Panday | 63 | 63 | 100 | Har Gar Jal | Not Certified |
| 6 | Basti | Vikramjot | Deokher | 450052 | Pure Hindu | 40 | 40 | 100 | Har Gar Jal | Not Certified |
| 7 | Basti | Vikramjot | Deokher | 680660 | Devekhar | 92 | 91 | 99 | Work In Progress | Not Certified |