Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | LC INFRA | 20085223 | RO SAKARA GRAM PANCHAYAT WATER SUPPLY SCHEME | 223.76 | 104.74 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 13859.00 | 13390.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | Sakra | 465802 | Sakra | 107 | 107 | 100 | Har Gar Jal | Not Certified |
| 2 | Mau | Ratanpura | Sakra | 465803 | Bijri | 24 | 13 | 54 | Work In Progress | Not Certified |
| 3 | Mau | Ratanpura | Sakra | 465804 | Vishunpur | 94 | 94 | 100 | Har Gar Jal | Not Certified |
| 4 | Mau | Ratanpura | Sakra | 465805 | Kirat Saray | 58 | 58 | 100 | Har Gar Jal | Not Certified |