Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20085281 | BHARHWAL SALEMPUR (GOGP) JJM | 351.41 | 214.05 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 10595.00 | 10595.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | MALLAWAN | DARAPUR | 413231 | DARAPUR | 234 | 234 | 100 | Har Gar Jal | Not Certified |
| 2 | Hardoi | MALLAWAN | BHARHWAL SALEMPUR | 413252 | BHARHWAL SALEMPUR | 288 | 288 | 100 | Har Gar Jal | Certified |