Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20085330
SCHEME NAME
RAGHUBANSHPUR URF RERUA WATER SUPPLY SCHEME
ESTIMATED COST
195.25
EXPENDITURE
101.70
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
10
Procured
10
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11647.00
Meter
Length Laid
11600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | SRINGVERPUR DHAM | RAGHUBANSHPUR URF RERUA | 431670 | RAGHUBANSHPUR URF RERUA | 400 | 375 | 94% | Work In Progress | Not Certified |