Scheme Details
DISTRICT
Azamgarh
AGENCY
SIEPL – BRCCPL (JV) / SKYLARK
SCHEME ID
20085337
SCHEME NAME
Sakar Kol Water Supply Scheme
ESTIMATED COST
238.46
EXPENDITURE
195.43
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13362.00
Meter
Length Laid
13129.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Ahiraula | Sankar Kola | 461512 | Sankar Kola | 145 | 145 | 100% | Har Ghar Jal | Not Certified |
| 2 | Azamgarh | Ahiraula | Sankar Kola | 461513 | Imeliya Mustakam Sankar Kola | 28 | 28 | 100% | Har Ghar Jal | Not Certified |
| 3 | Azamgarh | Ahiraula | Sankar Kola | 461514 | Chaktara | 16 | 14 | 88% | Work In Progress | Not Certified |
| 4 | Azamgarh | Ahiraula | Sankar Kola | 461515 | Junardar Patti | 36 | 36 | 100% | Har Ghar Jal | Not Certified |
| 5 | Azamgarh | Ahiraula | Sankar Kola | 461516 | Sankarpur | 23 | 23 | 100% | Har Ghar Jal | Not Certified |
| 6 | Azamgarh | Ahiraula | Sankar Kola | 461517 | Chitionee Baireeyad | 2 | 1 | 50% | Work In Progress | Not Certified |