| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | SIEPL – BRCCPL (JV) / SKYLARK | 20085338 | Sahuwal Water Supply Scheme | 284.48 | 114.00 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 13698.00 | 13696.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Ahiraula | Sahuwal | 461531 | Sahuwal | 149 | 146 | 98 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Ahiraula | Sahuwal | 461533 | Aslaipur | 71 | 69 | 97 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Ahiraula | Sahuwal | 461534 | Aslaipur Khurd | 9 | 8 | 89 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Ahiraula | Sahuwal | 461535 | Paryagpur | 79 | 79 | 100 | Har Gar Jal | Not Certified | 
| 5 | Azamgarh | Ahiraula | Sahuwal | 699825 | KATECIOLEE | 36 | 27 | 75 | Work In Progress | Not Certified |