| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20085426 | Harpur GP WSS | 233.37 | 122.58 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | NA | 0 | NA | No | 11188.00 | 11427.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Nathnagar | Harpur | 452693 | Harpur | 218 | 209 | 96 | Work In Progress | Not Certified | 
| 2 | Sant Kabeer Nagar | Nathnagar | Harpur | 452694 | Kishunpur | 35 | 11 | 31 | Work In Progress | Not Certified | 
| 3 | Sant Kabeer Nagar | Nathnagar | Harpur | 452695 | Bairagipur | 53 | 42 | 79 | Work In Progress | Not Certified |