Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20085514
SCHEME NAME
SEHUADEEH WATER SUPPLY SCHEME
ESTIMATED COST
192.02
EXPENDITURE
101.69
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12464.00
Meter
Length Laid
12464.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Phulpur | Sehuadeeh | 432434 | Sehuadeeh | 421 | 386 | 92% | Work In Progress | Not Certified |