Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20085519 | BANJARIA JJM SCHEME | 267.34 | 212.16 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 18 | 18 | Yes | 0 | NA | No | 27511.00 | 27000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Mohammadi | Banjariya | 408403 | Banjaria | 236 | 236 | 100 | Har Gar Jal | Certified | 
| 2 | Lakhimpur Kheri | Mohammadi | Banjariya | 408404 | Dulhapur | 80 | 80 | 100 | Har Gar Jal | Certified |