Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20085606
SCHEME NAME
RUKUNPUR
ESTIMATED COST
472.07
EXPENDITURE
458.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
10
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
32322.00
Meter
Length Laid
25091.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
10 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Rukunpur | 455993 | Rukunpur | 104 | 104 | 100% | Har Ghar Jal | Certified |
| 2 | Gorakhpur | Uruwa | Rukunpur | 455994 | Pakari | 57 | 57 | 100% | Har Ghar Jal | Certified |
| 3 | Gorakhpur | Uruwa | Rukunpur | 455995 | Baghi | 19 | 19 | 100% | Har Ghar Jal | Certified |
| 4 | Gorakhpur | Uruwa | Rukunpur | 455996 | Bourdih Bujurg | 55 | 55 | 100% | Har Ghar Jal | Certified |
| 5 | Gorakhpur | Uruwa | Rukunpur | 455997 | Bourdih Khurd | 87 | 87 | 100% | Har Ghar Jal | Certified |
| 6 | Gorakhpur | Uruwa | Rukunpur | 455998 | Bhawanpur | 20 | 20 | 100% | Har Ghar Jal | Certified |
| 7 | Gorakhpur | Uruwa | Rukunpur | 455999 | Mohanpur | 84 | 84 | 100% | Har Ghar Jal | Certified |
| 8 | Gorakhpur | Uruwa | Rukunpur | 456000 | Sukrouli | 75 | 75 | 100% | Har Ghar Jal | Certified |
| 9 | Gorakhpur | Uruwa | Rukunpur | 456001 | Chakrupaia | 3 | 3 | 100% | Har Ghar Jal | Certified |
| 10 | Gorakhpur | Uruwa | Rukunpur | 456002 | Pachperwa | 31 | 31 | 100% | Har Ghar Jal | Certified |