Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20085628
SCHEME NAME
Gulriha & Jaidpur Dehat Water Supply Scheme
ESTIMATED COST
516.05
EXPENDITURE
180.76
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23135.00
Meter
Length Laid
4622.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Harakh | Gulariha | 435323 | Gulariha | 340 | 340 | 100% | Har Ghar Jal | Certified |
| 2 | Barabanki | Harakh | JAIDPUR DEHAT | 435324 | PYARANPUR | 150 | 0 | 0% | Work In Progress | Not Certified |
| 3 | Barabanki | Harakh | JAIDPUR DEHAT | 435325 | JAIDPUR (DEHAT ) | 469 | 0 | 0% | Work In Progress | Not Certified |