Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Chandauli | ION EXCHANGE | 20085786 | Hinauta urf Jagdishrai WS | 269.17 | 75.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 10 | NA | No | 13429.00 | 13500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chandauli | Bhikharipur | 474671 | Bhikharipur | 279 | 249 | 89 | Work In Progress | Not Certified |
| 2 | Chandauli | Chandauli | Hinauta Urf Jagdishrai | 474677 | Hinauta Urf Jagdishrai | 403 | 363 | 90 | Work In Progress | Not Certified |
| 3 | Chandauli | Chandauli | Baratha | 474680 | Karshila | 146 | 122 | 84 | Work In Progress | Not Certified |
| 4 | Chandauli | Chandauli | Bichhiya Kala | 474753 | Bichhiya Kala | 245 | 209 | 85 | Work In Progress | Not Certified |