Scheme Details
DISTRICT
Chandauli
AGENCY
ION EXCHANGE
SCHEME ID
20085786
SCHEME NAME
Hinauta urf Jagdishrai WS
ESTIMATED COST
269.17
EXPENDITURE
86.86
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13429.00
Meter
Length Laid
13500.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chandauli | Bhikharipur | 474671 | Bhikharipur | 279 | 249 | 89% | Work In Progress | Not Certified |
| 2 | Chandauli | Chandauli | Hinauta Urf Jagdishrai | 474677 | Hinauta Urf Jagdishrai | 403 | 363 | 90% | Work In Progress | Not Certified |
| 3 | Chandauli | Chandauli | Baratha | 474679 | Baratha | 75 | 75 | 100% | Har Ghar Jal | Not Certified |
| 4 | Chandauli | Chandauli | Baratha | 474680 | Karshila | 146 | 122 | 84% | Work In Progress | Not Certified |
| 5 | Chandauli | Chandauli | Baratha | 474681 | Kishundaspur | 10 | 10 | 100% | Har Ghar Jal | Not Certified |
| 6 | Chandauli | Chandauli | Bichhiya Kala | 474753 | Bichhiya Kala | 245 | 235 | 96% | Work In Progress | Not Certified |