Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20085840
SCHEME NAME KALAKAND & BIHARIPUR AJAB WATER SUPPLY SCHEME
ESTIMATED COST 437.38
EXPENDITURE 91.56
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 16272.00 Meter
Length Laid 16272.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Dataganj Kalakand 402290 Kalakand 214 213 100% Work In Progress Not Certified
2 Budaun Dataganj Kalakand 402291 Bheda 91 90 99% Work In Progress Not Certified
3 Budaun Dataganj Kalakand 402292 Diyouhari 116 116 100% Har Ghar Jal Not Certified
4 Budaun Dataganj Biharipur Ajab 402304 Biharipur Ajab 226 225 100% Work In Progress Not Certified