Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20085840
SCHEME NAME
KALAKAND & BIHARIPUR AJAB WATER SUPPLY SCHEME
ESTIMATED COST
437.38
EXPENDITURE
91.56
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16272.00
Meter
Length Laid
16272.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Dataganj | Kalakand | 402290 | Kalakand | 214 | 213 | 100% | Work In Progress | Not Certified |
| 2 | Budaun | Dataganj | Kalakand | 402291 | Bheda | 91 | 90 | 99% | Work In Progress | Not Certified |
| 3 | Budaun | Dataganj | Kalakand | 402292 | Diyouhari | 116 | 116 | 100% | Har Ghar Jal | Not Certified |
| 4 | Budaun | Dataganj | Biharipur Ajab | 402304 | Biharipur Ajab | 226 | 225 | 100% | Work In Progress | Not Certified |