Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Chandauli
AGENCY ION EXCHANGE
SCHEME ID 20085853
SCHEME NAME Barahani WS
ESTIMATED COST 229.83
EXPENDITURE 73.15
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 0
Work Started 0
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 10
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11110.00 Meter
Length Laid 11000.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Chandauli Barhani Barahani 474911 Barahani 401 370 92% Work In Progress Not Certified
2 Chandauli Barhani Barahani 474912 Parsiya 104 104 100% Har Ghar Jal Not Certified