Scheme Details
DISTRICT
Mau
AGENCY
KLSR - RAYS (JV)
SCHEME ID
20085983
SCHEME NAME
AMARSEPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
174.74
EXPENDITURE
71.19
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8153.00
Meter
Length Laid
7522.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ranipur | Amarsepur | 466195 | Amarsepur | 76 | 75 | 99% | Work In Progress | Not Certified |
| 2 | Mau | Ranipur | Amarsepur | 466196 | Gaganpur | 25 | 24 | 96% | Work In Progress | Not Certified |
| 3 | Mau | Ranipur | Amarsepur | 466197 | Rukum Zanib | 29 | 27 | 93% | Work In Progress | Not Certified |
| 4 | Mau | Ranipur | Amarsepur | 466198 | Khurd Karmi | 54 | 50 | 93% | Work In Progress | Not Certified |