Scheme Details
DISTRICT
Raebareli
AGENCY
U.P.Jal Nigam
SCHEME ID
20085997
SCHEME NAME
BARAMJITPUR URF KHWATA G.O.V.
ESTIMATED COST
958.80
EXPENDITURE
57.34
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Record Not Found
Scheme Assigned Villages
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Rohiniyan | Sareni | 417545 | Sareni | 350 | 350 | 100% | Har Ghar Jal | Certified |
| 2 | Raebareli | Rohiniyan | Itaili | 417549 | Itaili | 210 | 167 | 80% | Work In Progress | Not Certified |
| 3 | Raebareli | Rohiniyan | Itaili | 417550 | Hari Vanshpur | 52 | 3 | 6% | Work In Progress | Not Certified |
| 4 | Raebareli | Rohiniyan | Matrampur | 417553 | Matrampur | 287 | 256 | 89% | Work In Progress | Not Certified |
| 5 | Raebareli | Rohiniyan | Matrampur | 417554 | Loharani | 23 | 10 | 43% | Work In Progress | Not Certified |
| 6 | Raebareli | Rohiniyan | Matrampur | 417555 | Suhapar | 44 | 2 | 5% | Work In Progress | Not Certified |
| 7 | Raebareli | Rohiniyan | Hamid Pur Bada Gaon | 417559 | Hamid Pur Badagaon | 201 | 187 | 93% | Work In Progress | Not Certified |
| 8 | Raebareli | Rohiniyan | Hamid Pur Bada Gaon | 417560 | Bhikhnapur Klapur | 81 | 77 | 95% | Work In Progress | Not Certified |
| 9 | Raebareli | Rohiniyan | Hamid Pur Bada Gaon | 417561 | Bramh Jitpur(khovata) | 107 | 89 | 83% | Work In Progress | Not Certified |